Resource-constrained scheduling

Also called minimum-latency resource-constrained scheduling, ML-RCS.

Assign each operation of a sequencing graph to a control step so that no step uses more units of a type than allowed and the latency is least; NP-hard in general.

Resource-constrained scheduling is the scheduling problem of high-level synthesis in which the number of functional units of each type is fixed and the goal is the shortest schedule. The input is a sequencing graph of operations, the data flow graph of one block of a control data flow graph, with a delay and a unit type for each operation. A schedule gives each operation a start step. It must respect the data edges, and in no step may more operations of one type run than there are units of that type. With one type and unit delays it is the classic problem of scheduling unit tasks with precedences on mm processors, which Ullman proved NP-complete in 1975. The partner problem, which fixes the latency and minimizes the units, is latency-constrained scheduling.

In plain words

You have a list of calculations, some of which need the result of others. You have, say, two multipliers and one adder, and each clock tick a unit can start one calculation. You want to finish everything in as few ticks as possible. The order of the needs gives a lower limit, because a long chain of dependent steps cannot be squeezed. The number of units gives another limit, because six multiplies on two multipliers need at least three ticks. The hard part is that both limits act at the same time, and a choice that looks good early can block a long chain later.

Definition

Input.

  • A sequencing graph G=(V,E)G = (V, E) with no cycle.
  • For each operation v∈Vv \in V, an integer delay d(v)≥1d(v) \ge 1 in clock cycles and a type t(v)t(v) from a set KK of unit types.
  • For each type k∈Kk \in K, a number of units ak≥1a_k \ge 1.

Feasible solutions. A schedule is a map s:V→{0,1,2,…}s : V \to \{0, 1, 2, \ldots\} of start steps with

  • s(v)≥s(u)+d(u)s(v) \ge s(u) + d(u) for each edge (u,v)∈E(u, v) \in E, and
  • ∣{v:t(v)=k, s(v)≤j<s(v)+d(v)}∣≤ak\left|\{ v : t(v) = k,\ s(v) \le j < s(v) + d(v) \}\right| \le a_k for each type kk and each step jj.

An operation keeps its unit busy for all of its d(v)d(v) cycles: units are not pipelined. Each step is one clock cycle, and two dependent operations never share a step: there is no chaining.

Objective. Minimize the latency λ(s)=max⁡v∈V(s(v)+d(v))\lambda(s) = \max_{v \in V} (s(v) + d(v)), the number of steps until the last operation ends. With a source and a sink of delay 0, as in De Micheli's sequencing graphs, this equals s(sink)−s(source)s(\text{sink}) - s(\text{source}).

Decision form. Given the input and an integer λ0\lambda_0, is there a schedule with λ(s)≤λ0\lambda(s) \le \lambda_0?

Variants

  • Pipelined units. A unit of type kk accepts a new operation every cycle, even though each result takes d(v)d(v) cycles. Then an operation occupies its unit only in its first step, and the resource row counts s(v)=js(v) = j only.
  • Chaining. Delays are real numbers and the clock period TT is given. Dependent operations may share a step when the sum of their delays fits in TT. See operation chaining.
  • Several unit types per operation. An operation can run on more than one type, for example an add on an adder or on an ALU, with different delays. Choosing the type is module selection.
  • Control flow. Operations on different arms of a branch never run together, so they can share a unit in the same step. Schedulers for a whole CDFG, such as path-based scheduling, use this.
  • Loops. For a loop body that starts a new iteration every IIII cycles, the resource rows count operations modulo IIII. This is modulo scheduling, as in SDC modulo scheduling.
  • Timing constraints. Upper and lower bounds on the distance between two starts, such as s(v)−s(u)≤cs(v) - s(u) \le c, are added rows. They can make the instance infeasible for every latency.

Examples

Take the differential equation example of Paulin and Knight, with the operations, types and edges that the high-level synthesis page gives: six multiplies, five ALU operations, unit delays and a critical path of 4 steps. The least latency for each pair of unit counts is

multipliers ALUs least latency
1 1, 2 or 3 7
2 1 5
2 2 or 3 4
3 1 5
3 2 or 3 4

With one multiplier, the six multiplies need 6 steps, and the last of them feeds an ALU operation, so 7 steps is a lower bound and it is reached. With two multipliers and two ALUs, the latency meets the critical path of 4. A third multiplier never helps here: the multiplies are not the limit once there are two.

For a small case where the choice in one step matters, take one type with two units, a chain c1→c2→c3c_1 \to c_2 \to c_3, and three operations x,y,zx, y, z with no edges, all of delay 1. Both lower bounds below give 3 steps. If step 0 runs xx and yy, the chain starts one step late and the latency is 4. If step 0 runs c1c_1 and xx, then step 1 runs c2c_2 and yy, and step 2 runs c3c_3 and zz, which gives 3. So a good schedule starts the long chain first, which is why list schedulers rank ready operations by the length of the path below them.

Known algorithms

  • List scheduling. Step by step, start the ready operations with the highest priority, up to aka_k per type. It is fast and not exact. See list scheduling, and for the bound for one type, the list scheduling bound.
  • Hu's algorithm. Exact when there is one type, unit delays and the graph is an in-tree. See Hu's algorithm.
  • Coffman and Graham. Exact for one type with two units and unit delays. See the Coffman-Graham algorithm.
  • Integer programming. A 0-1 program with one variable per operation and step gives the optimum for small graphs. See the ILP formulation.
  • SDC scheduling. Writes the resource bounds as extra difference constraints from a fixed order and solves an LP. It is fast and not exact under resource bounds. See SDC scheduling.
  • Force-directed list scheduling. List scheduling that defers the ready operations whose deferral has the least force, by Paulin and Knight. See force-directed scheduling.
  • Branch and bound. Search over the choices of each step, cut off by the lower bounds below. See depth-first branch and bound.
AlgorithmTimeSpacePropertiesCode
Path-based schedulingO(P V^2 log V + R (R V + E log E)) worstO(P V + R V) extradeterministicnot exactofflineiterative1 language
SDC-based modulo schedulingO(I P V^2 (V + E)) worstO(V + E) extradeterministicnot exactofflineiterative1 language
SDC-based schedulingO(V (V + E) + V C) worstO(V^2 + C) extradeterministicnot exactofflineiterative1 language

Bounds

Let CP\mathrm{CP} be the critical path, the largest sum of delays on a path of GG, and let Wk=∑t(v)=kd(v)W_k = \sum_{t(v) = k} d(v) be the work of type kk.

Lower bound. Every schedule has λ≥max⁡(CP,max⁡k⌈Wk/ak⌉)\lambda \ge \max(\mathrm{CP}, \max_k \lceil W_k / a_k \rceil). The first term holds because the operations of a path run one after another. The second holds because each step gives at most aka_k busy cycles of type kk.

Upper bound for any greedy list schedule. Call a list schedule greedy if it never leaves a unit of type kk idle in a step where an operation of type kk is ready and waiting. Then, with ∣K∣|K| unit types,

λ≤CP+∑k∈KWkak≤(∣K∣+1) λ∗.\lambda \le \mathrm{CP} + \sum_{k \in K} \frac{W_k}{a_k} \le (|K| + 1)\,\lambda^*.

Proof: let v1v_1 be an operation that ends last. Given viv_i, let vi+1v_{i+1} be a predecessor of viv_i that ends last, and stop when viv_i has no predecessor. This is a path, so the steps in which some viv_i runs number at most CP\mathrm{CP}. Take any other step jj before the end. It lies between the end of some vi+1v_{i+1} and the start of viv_i, or before the start of the first one. In that step all predecessors of viv_i have ended, so viv_i is ready and waiting, and by greed all at(vi)a_{t(v_i)} units of its type are busy. A step in which all units of type kk are busy uses aka_k cycles of the work WkW_k, so there are at most Wk/akW_k / a_k such steps for each kk. Adding up gives the first inequality, and each term is at most λ∗\lambda^* by the lower bound. For one type the bound is 2λ∗2 \lambda^*, and Graham's finer analysis gives 2−1/a2 - 1/a. With chaining or with timing constraints, this argument fails, because a ready operation may be unable to start for reasons other than busy units.

Hardness of approximation. For one type and unit delays, deciding whether λ∗≤3\lambda^* \le 3 is NP-complete (Lenstra and Rinnooy Kan, 1978). So no polynomial algorithm guarantees a latency below 43λ∗\tfrac43 \lambda^* unless P = NP.

Reductions

In NP. A schedule with λ≤λ0\lambda \le \lambda_0 has all starts below λ0\lambda_0, so it can be written down and checked against every edge and every step in polynomial time when λ0\lambda_0 is at most ∑vd(v)\sum_v d(v). A larger λ0\lambda_0 makes the answer trivially yes, because running the operations one at a time in a topological order takes ∑vd(v)\sum_v d(v) steps.

NP-hard (Ullman 1975). The special case with one type, d(v)=1d(v) = 1 for all vv and aa units is the problem of scheduling unit-time tasks with precedences on aa processors to finish by a deadline. A schedule here is the same object as a processor schedule there: a start step for each task, with at most aa tasks per step, and each task after its predecessors. Ullman proved this problem NP-complete when aa is part of the input. So the decision form above is NP-complete, and the optimization form is NP-hard. All numbers in the hard instances are small, so the problem is NP-hard in the strong sense.

Small cases. For one type and a fixed number a≥3a \ge 3 of units, the complexity is a long-standing open problem from the list of Garey and Johnson. For a=2a = 2 and unit delays, the Coffman-Graham algorithm solves it, and for in-trees with any aa, Hu's algorithm does.

To latency-constrained scheduling. The decision form is the same question as the decision form of latency-constrained scheduling: units aka_k and latency λ0\lambda_0. So a polynomial algorithm for either optimization form would answer it, and both are NP-hard.

Applications

  • High-level synthesis. Schedule each block of a CDFG when the designer fixes the units, for example to fit an area budget or an FPGA with few DSP blocks.
  • Instruction scheduling. A compiler for a processor with fixed functional units solves the same problem on each basic block. See the instruction scheduling problem.
  • Project scheduling. Tasks with precedences and limited crews or machines give the same model with general delays.
  • Design space exploration. Solving it for each unit vector gives the latency side of the area and latency trade-off curve.

References

  1. Giovanni De Micheli, Synthesis and Optimization of Digital Circuits, McGraw-Hill, 1994, Chapter 5, Scheduling Algorithms (the section on scheduling with resource constraints)
  2. J. D. Ullman, NP-complete scheduling problems, Journal of Computer and System Sciences 10(3), 1975, the NP-completeness of scheduling unit-time tasks with precedence constraints on a given number of processors
  3. J. K. Lenstra and A. H. G. Rinnooy Kan, Complexity of scheduling under precedence constraints, Operations Research 26(1), 22 to 35, 1978, deciding whether unit-time tasks with precedences fit in three steps on a given number of processors is NP-complete
  4. Pierre G. Paulin and John P. Knight, Force-directed scheduling for the behavioral synthesis of ASICs, IEEE Transactions on Computer-Aided Design 8(6), 661 to 679, 1989, resource-constrained scheduling by force-directed list scheduling, and the differential equation example
  5. Michael R. Garey and David S. Johnson, Computers and Intractability, A Guide to the Theory of NP-Completeness, W. H. Freeman, 1979, the list of open problems (precedence-constrained scheduling of unit tasks on a fixed number of processors)

Where this leads

About this page

The build computes these levels from the evidence in the repository. Each row says what the next level needs. Read what the levels mean.

LadderLevelWhat the next level needs
Human proofH0 no proof
  • add a proof in proofs/ (06.5)
LeanL0 no Lean part
  • name a Lean module in the lean field (07)
VisualV0 none
  • add viz/scene.ts or a figure (10)
WritingW2 basic
  • a contract.yaml